start date: 2021-09-01
№ | Contract Subject | ID | Date | Publication Date | Contract Price | Contractor |
1 | Supply and installation contract for security systems | AP-04 | 9/3/2021 | 04.09.2021 | 5 700 000 (including VAT) | CJSC "PATRAS" |
2 | Contract for the restoration of the decomposed part of the foundation of the retaining wall of Argel HPP | AKH-11 | 13.09.2021 | 14.09.2021թ | 16 174 377 (including VAT) | "TEKS" CJSC |
3 | Contract for the repair of emergency drainage canal of the Arzni HPP | AKH-12 | 13.09.2021 | 14.09.2021թ | 8 572 386 (including VAT) | "T-Construction" CJSC |
4 | Contract for the repair of the wooden structures of the dam and the building of the checkpoint of Kanaker HPP | AKH-13 | 13.09.2021 | 14.09.2021թ | 3 470 553 (including VAT) | "Inteko Energo" CJSC |
5 | Contract for the reconstruction of the ball valve and parts of hydroelectric unit N2 of Arzni HPP, IEC CJSC | GB-36 | 9/27/2021 | 9/29/2021 | 41 983 367.13 (including VAT) | "Energanorogum"OJSC |
6 | Contract for the reconstruction of the ball valve of the hydroelectric unit No. 2 of Argel HPP, IEC CJSC | GB-37 | 9/28/2021 | 9/29/2021 | 35 125 345.52 (including VAT) | "Energanorogum"OJSC |
7 | Contract for the reconstruction of the ball valve and parts of hydroelectric unit N2 of Hrazdan HPP, IEC CJSC | GB-38 | 9/28/2021 | 9/29/2021 | 19 999 189.53 (including VAT) | "Energanorogum"OJSC |
8 | Contract for the reconstruction of the ball valve and parts of the hydroelectric unit No. 2 of the Hrazdan HPP at the station, IEC CJSC | GB-39 | 9/28/2021 | 9/29/2021 | 18 574 093.30 (including VAT) | "Energanorogum"OJSC |
9 | Contract for the reconstruction of the butterfly valve and parts No. 5 of the hydroelectric unit of the Kanaker HPP, IEC CJSC | GB-40 | 9/29/2021 | 9/30/2021 | 30 729 264.14 (including VAT) | "Energanorogum"OJSC |